Case Study 1: Perenco (Bacton Gas Terminal) 2020
- Close out of HAZOP actions and recalculation of 53 relief valves for onshore gas processing terminal.
- Failure scenarios assessed, valves sized, actions highlighted.
- Safety report issued to client for implementation.
Case Study 2: Ineos (FPS Kinneil) 2023
- Flarenet analysis of a crude relief line and flare system.
- Developed optimisation of sizing including recommendations for resizing existing valves where capacities exceeded requirements and the excess flow was contributing to excessive pressure drop, vibration and slugging.
- Resized valves and relief line leads to significantly reduced sizing, improved layout, installation and flow regime, along with reduction in CAPEX.
Case Study 3: Shell UK Limited (Acorn CCS) 2022
- WHRU & Heating Medium System Analsysis for Carbon Capture Plant
- Proved the requirement for a secondary heating medium loop system for flue gas cooling & providing heat to the Amine reboiler.
- Developed process simulation & calculations for heat integration & equipment sizing / optimisation.
- Delivered report with recommendations to client’s satisfaction